Project info

  • Construction, Environment Designs
  • New Urban Communities Authority
    New City of Qena Authority.

  • In progress

  • Qena Governorate.

  • 290000000 EGP

Project overview

The project consists of a sewage treatment plant with an oxidation ditch system, with a capacity of 15,500 m3/day for secondary treatment. It also involves implementing a tertiary treatment system with a capacity of 15,500 m3/day and a corresponding discharge line measuring 18,500 meters in length, located in New Qena City.

  • 18,025 meters of the discharge line have been executed, and 33 out of a total of 37 chambers have been completed, achieving a completion rate of 92%.
  • The construction of the station buildings has been completed at a rate of 80%.
  • The basins have been completed at a rate of 85%.

Challenge

The fluctuation in the exchange rate has negatively impacted the delivery schedule of electromechanical equipment.

Result

The project works have been executed so far at a rate of 82%.