Project info

  • Construction, Environment Designs
  • National Water and Sanitation Authority.

  • Currently being executed.

  • Sohag Governorate - Tama Center - Al-Midmar Village.

  • 262,127,350 EGP

Project overview

Project for the design and implementation of a gravity network, including (2) pumping stations (main and sub), and (2) discharge lines.

Challenge

Citizen awareness about the importance of sanitation for the village – objection from some citizens to excavation works in the streets – existence of unknown utility networks without coordinates – presence of water lines, chambers, and electrical cables hindering the implementation.

Result

Most of the obstacles have been overcome, and implementation is ongoing until the completion of the project to serve 9 villages.