Project info

  • Construction, Environment Designs
  • The main contractor - Military Production for Projects and Engineering Consultations.

  • Currently being executed

  • Bani Khalid Village, Minya Governorate.

  • 62120000 EGP

Project overview

The project consists of the comprehensive sanitation system for Bani Khalid Village – Mallawi Center – Minya Governorate (gravity networks – pumping station – discharge line)

Challenge

  1. Groundwater at a depth of 0.8 meters.
  2. Narrow streets and the presence of electrical cables, telephone lines, and water pipes conflicting with the sewer lines.

As for Tuna:

  1. The entire project is built on rocky land with a resistance of 350-500 kg/cm².
    Narrow roads leading to the project.
  2. Multiple projects are being implemented in neighboring villages concurrently, leading to road closures leading to the project.

Result

Approximately 92% of the civil works for the project have been completed.